By Dr Sanjay Chaturvedi, LLB PhD. Real Estate (Regulation and Development) Act 2016 was enacted to safeguard the interest and rights of property purchasers. Ever since the Act is enacted, hundreds and thousands of complaints against builders were registered and resolved in the country. It is observed that it is habitual

Oral promise of possession under RERA Act tenable?

Whether a promoter is required to enclose commencement certificate obtained from the competent authority while submitting an application for registration of his project as per Section 4(2)(c) of Real Estate (Regulation and Development) Act, 2016? By Dr. Sanjay Chaturvedi, LLB, Ph.D. Umesh Magar and other various complainants V/s Kul Developers Pl't. Ltd

Agreement for Sale was executed in MOFA hence no jurisdiction of RERA?

By Dr. Sanjay Chaturvedi LLB, Ph.D. Avinash Saraf, Neha Duggar Saraf V/s. Runwal Homes Pvt. Ltd (CC006000000000032) Order dated 13th Oct 2017 The Complainants contend that they have paid 97% of total consideration of the said flat. The respondent has specified in the agreement of sale that the possession of the flat

Is Society Redevelopment having jurisdiction of RERA?

By Sanjay Chaturvedi LLB, Ph.D. Himbindu Co-operative Housing Society V/s Mr. Jitendro Shankarlal Brahmbhatt (CC@6000000001577) Order dated: 5th Jan 2018 The complainant Society, through it's Secretary, has filed this complain seeking following directions from this Authority a) To register the Second Supplementary agreement doted 23rd August 2015 on payment of all dues within

Whether fully constructed building without constructing common areas and without providing agreed amenities but occupied by all flat purchasers without occupancy/completion certificate as on the date of commencement of RERA, amounts to ongoing project? Yes!

By Dr. Sanjay Chaturvedi LLB, Ph.D. Parag Pratap Mantri V/s Green Space Developers (CC0050m000000136) Order dated 5th February 2018 by Maha RERA The complainant alleges that though the respondents have not received completion certificate of E-wing/ building, they have not registered the same with Maha RERA and thereby they contravened Section 3

Will Arbitration Agreement come under RERA? Co-purchaser also Allotee?

By Sanjay Chaturvedi LLB, PhD Mr. Ganesh Lonkar V/s D.S. Kulkarni Developers Ltd. (CC005000000000317) Order 26th December 2017 Whether the Arbitration Agreement will oust the jurisdiction of Maha RERA and whether the complaint filed by a co-purchaser is maintainable?, are the important legal issues involved in this complaint filed under section 18

20:80 Subvention Scheme covered under Section 18 if Agreement for Sale is Executed

By Dr. Sanjay Chaturvedi, LLB, Ph.D. Naman Agarwal & Others V/s Reliance Enterprises and Dewan Housing Finance Ltd (CC006000000001788) Order dated: 28th March 2018 The complainants have filed this complaint u/s. 18 of Real Estate Regulation and Development, Act 2016 (RERA). They contend that they booked Apartment No. 904, A-Wing of Respondent